Step-by-step instruction

Algorithm for the implementation of the investment project

From the beginning of the implementation of the investment project to its full completion, the entrepreneur passes the following procedures:

Obtaining a land plot

After the entrepreneur presented his project, he initiated a letter addressed to the region/district authorities about the intentions of the investment project, the process of recognizing this project as an investment project is launched, by submitting it to the Regional Coordination Council for consideration.

Further in the table are presented the step-by-step measures for obtaining the state act on the land plot.

 

Task

Responsible

Timing

The basis (the protocol of the Regional Coordination Council, the recognition of the project as an investment project)

Department of entrepreneurship and industrial-innovative development of Atyrau region

1 month

Statement

Initiator

1 day

Land commission

(formalized in a protocol)

Akimat of city/district

5-30 days

Land project

Initiator

7 days

Decree of akim of the city, district

Akimat

5-30 days

Obtaining of the State Act on the land plot

(and his registration at the Public Service Center)

Public Service Center

7 days

After the initiator starts to develop an architectural planning task, having received the following documents:

 

Task

Responsible

Timing

Obtaining technical specification for communication

Subjects of natural monopoly

7 days

Conducting of dosimetric control (parallel to obtaining technical specifications)

Regional sanitary and epidemiological station

2 days

Obtaining the conclusion of the sanitary-epidemiological service

(in parallel with the receipt of technical specifications)

Regional sanitary and epidemiological station, consumer protection department.

15 days

Architectural planning task

Department of Architecture/ Public Service Center

7 days

Then it goes on to the development of design estimates, on average, it takes about 5 months.

 

 

Task

Responsible

Timing

Development of a draft design

Investor

15 days

Passage of the town-planning council of the region

Regional department of Architecture

1 month

Approval of a draft design

City/district department of Architecture

15 days

Development of design estimates

Investor

10-60 days

Passage of the State Expertise

(depending on the project, it is possible to pass a private expertise)

State expertise / private expertise

45 days

After all the design documentation is developed and approved, the initiator receives a notification of the beginning of construction and installation works and proceeds to them.

 

Task

Responsible

Timing

Receiving notification of the beginning of construction and installation work

Department of state architectural and construction control

3 days

Construction and installation work

Initiator / general contractor

6-24 months

Commissioning Act

(receipt of an act of commissioning)

Initiator