Algorithm for the implementation of the investment project
From the beginning of the implementation of the investment project to its full completion, the entrepreneur passes the following procedures:
Obtaining a land plot
After the entrepreneur presented his project, he initiated a letter addressed to the region/district authorities about the intentions of the investment project, the process of recognizing this project as an investment project is launched, by submitting it to the Regional Coordination Council for consideration.
Further in the table are presented the step-by-step measures for obtaining the state act on the land plot.
Task |
Responsible |
Timing |
|
The basis (the protocol of the Regional Coordination Council, the recognition of the project as an investment project) |
Department of entrepreneurship and industrial-innovative development of Atyrau region |
1 month |
|
Statement |
Initiator |
1 day |
|
Land commission (formalized in a protocol) |
Akimat of city/district |
5-30 days |
|
Land project |
Initiator |
7 days |
|
Decree of akim of the city, district |
Akimat |
5-30 days |
|
Obtaining of the State Act on the land plot (and his registration at the Public Service Center) |
Public Service Center |
7 days |
After the initiator starts to develop an architectural planning task, having received the following documents:
|
Task |
Responsible |
Timing |
Obtaining technical specification for communication |
Subjects of natural monopoly |
7 days |
|
Conducting of dosimetric control (parallel to obtaining technical specifications) |
Regional sanitary and epidemiological station |
2 days |
|
Obtaining the conclusion of the sanitary-epidemiological service (in parallel with the receipt of technical specifications) |
Regional sanitary and epidemiological station, consumer protection department. |
15 days |
|
Architectural planning task |
Department of Architecture/ Public Service Center |
7 days |
Then it goes on to the development of design estimates, on average, it takes about 5 months.
|
Task |
Responsible |
Timing |
Development of a draft design |
Investor |
15 days |
|
Passage of the town-planning council of the region |
Regional department of Architecture |
1 month |
|
Approval of a draft design |
City/district department of Architecture |
15 days |
|
Development of design estimates |
Investor |
10-60 days |
|
Passage of the State Expertise (depending on the project, it is possible to pass a private expertise) |
State expertise / private expertise |
45 days |
After all the design documentation is developed and approved, the initiator receives a notification of the beginning of construction and installation works and proceeds to them.
|
Task |
Responsible |
Timing |
Receiving notification of the beginning of construction and installation work |
Department of state architectural and construction control |
3 days |
|
Construction and installation work |
Initiator / general contractor |
6-24 months |
|
Commissioning Act (receipt of an act of commissioning) |
Initiator |